Proposed Rule Timeline - Farmworker Housing Recovery Program and Special Housing Assistance and Development Program
   
 
Proposed Date*     Description
1/26/2007     Rule Development Workshop (in conjunction with Board Meeting); Begin Comment Period
3/14/2007     End Comment Period
4/13/2007 Rule adopted
4/13/2007 Open FHRP/SHADP cycle (75 days)
4/21/2007 Application Workshop (After Board Meeting)
6/22/2007 Close FHRP/SHADP cycle
7/11/2007 Preliminary Scores issued
7/19/2007 NOPSEs due
8/1/2007 NOPSE Scores issued
8/13/2007 Cures due
8/27/2007 NOADs due
8/31/2007 Issue Final Scores and Notice of Rights
Early November 07 Informal Appeal Hearings
1/25/2008 Board approves final ranking for FHRP/SHADP Application
1/28/2008 Staff issues Final Ranking Scores

*Tentative Dates, Subject to Change

Click here to download a printable (PDF) version